These Exam Resources updates are supplied free of charge to Exam-Certification customers. If you have any question about Oracle 1Z0-964 braindumps, please feel free to contact us at any time. Prepare for the Oracle 1Z0-964 Certification Testpassport scan all chapters of official publications and make a detailed plan for Oracle 1Z0-964 Certification Exam.

Besides, Testpassport also got a high reputation in many certification industry. The the probability of passing Oracle certification 1Z0-964 exam is very small, but the reliability of Testpassport can guarantee you to pass the examination of this probability. Testpassport Oracle certification 1Z0-964 dumps pdf can test your knowledge in preparing for the exam, and can evaluate your performance within a fixed time. The instructions given to you for your weak link, so that you can prepare for the exam better.
Share some Software as a Service – Oracle Enterprise Resource Planning Cloud 1Z0-964 exam questions and answers below.
Identify two correct role templates available on the Oracle Entitlement Server to generate roles for Project Organization Security. (Choose two.)

A. Project Manager Template for Project Organization Security

B. Project Administrator Template for Project Organization Security

C. Project Creator Template for Project Organization Security

D. Project Accountant Template for Project Organization Security

E. Project Billing Specialist Template for Project Organization Security

Answer: A,D

As you go through the first-quarter close for your customer, you notice that the burden amounts calculated do not seem to be right. Based on the calculations, you notice that the amounts calculated are not considering the burden schedule override at a task level, which was done during the second month of the quarter.Identify the reason for this problem. (Choose the best answer.)

A. Only new expenditure items charged to the task use the new burden schedule; expenditure items processed earlier cannot be reprocessed.

B. Only new expenditure items charged to the task use the new burden schedule; expenditure items processed earlier can be manually marked for reprocessing.

C. You can enable automatic reprocessing of expenditure items processed before the burden schedule change.

D. All expenditure items charged to the task use the new burden schedule.

Answer: B

Your client is involved in automation control systems installation. Over the years, they have analyzed their total project spend on specific resource classes. They have identified that their cost spread distribution factor on a 10 spread point scale resembles: 0-4-10-11-14-13-10-4-0-0.Identify two ways to handle this kind of a spread on their budgets and forecasts. (Choose two.)

A. Create a new spread curve or edit an existing spread curve to exactly match the spread points and attach to a project template.

B. Create a new spread curve or edit an existing spread curve to exactly match the spread points and attach to the resource class.

C. Use the predefined Bell Curve spread with small deviations on the spread points.

D. Use the predefined S-Curve spread with small deviations on the spread points.

Answer: B,C

Your customer has different accounting and project accounting periods, and sometimes enters invoices with an invoice date in the open project accounting and closed accounting periods. Which two statements are true about how project accounting and accounting dates will be populated in such invoices? (Choose two.)

A. Accounting date is the same as the original invoice date.

B. Project accounting date is the same as the original invoice date.

C. Project accounting date is the first day of the first open project accounting period.

D. Project accounting date is the last day of the open project accounting period.

E. Accounting date is the first day of the first open accounting period.

Answer: C,E

Identify the precedence order in which cost rates are determined for a planning resource when deriving raw costs for rate-based planning resources. (Choose the best answer.)

A. Override rate > Job rate schedule > Resource class rate schedule > Person rate schedule

B. Person rate schedule > Job rate schedule > Resource class rate schedule > Override rate

C. Job rate schedule > Resource class rate schedule > Override rate > Person rate schedule

D. Override rate > Person rate schedule > Job rate schedule > Resource class rate schedule

E. Resource class rate schedule > Override rate > Job rate schedule > Person rate schedule

Answer: D

This syllabus highlights the most vital and anticipated contents regarding the test and exclude all of the unnecessary details. Thus, It provides a shortcut way and prevents you from over digesting the whole of Oracle certification 1Z0-964 dumps pdf. Let is to smooth your way and make your scores higher to get Oracle Project Portfolio Management Cloud 2017 Implementation Essentials. If you buy Testpassport Oracle certification 1Z0-964 dumps pdf, you can not only pass Oracle certification 1Z0-964 exam, but also enjoy a year of free update service.